Bluffton Parkway flyover beams placed

Published at 1:41 p.m. on June 20, 2014 | Modified at 1:42 p.m. on June 20, 2014

In video shot by John Nguyen of F&ME Consultants and supplied by Beaufort County, construction workers place 90-foot concrete beams on columns comprising the Bluffton Parkway flyover connecting the parkway to the Karl Bowers Bridge. At the time of the video, 36 beams were placed, with 138 remaining, as well as 30 steel beams. The $36-million flyover is scheduled for completion in November 2015.

The Island Packet is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.