Analysis: BRAC savings tainted by cost overruns

The Washington PostJuly 8, 2012 

  • Local leaders and business officials have expressed concern about protecting Beaufort County's three military bases from closure.

    Marine Corps Recruit Depot Parris Island, Marine Corps Air Station Beaufort and Naval Hospital Beaufort were spared during five previous BRAC examinations, most recently in 2005, and local officials say they will fight for a similar outcome if the commission reconvenes.

    Using $250,000 in funds from Beaufort County, the Beaufort Regional Chamber of Commerce plans to build awareness locally about the economic and cultural value of the three bases and to hire a lobbyist in Washington. Chamber officials have said they also plan to seek contributions from local municipalities and the area's business community.

    The installations employ about 5,300 people.

A proposal to grant the Obama administration the authority to start two new rounds of military Base Realignment and Closure appears dead on arrival on Capitol Hill, and the Government Accountability Office probably hammered the final nail in the coffin June 29.

In its latest review of the 2005 BRAC program -- the largest and most complex -- the GAO found that the preliminary estimate of $21 billion to implement the program had grown to $35 billion by Sept. 30, 2011.

Indeed, the BRAC process seems to be just another story of uncontrolled Pentagon spending with almost no public attention.

The 67 percent increase in what BRAC's 2005 program was supposed to cost and its actual cost "was largely due to increased construction costs" linked primarily to just 14 of the 180 projects approved, the GAO said.

The report's stun factor wasn't limited to mistakes in planning and calculations. It seems that no one in these cases stepped back to try a less costly path.

Take the consolidation of various National Geospatial-Intelligence Agency locations at a new campus at Fort Belvoir, Va.

A project projected to cost $1.1 billion grew to a price tag of $2.6 billion. About $726 million of the increase happened because the agency did not foresee its need for support facilities, including a new technology center and data-storage warehouse of 200,000 square feet. Also not included in initial estimates for the NGA Campus East were "costs for information technology equipment and software, internal communication cabling, and furnishings to outfit the new buildings," according to the GAO.

A misjudgment about space was also involved in a $1.1 billion increase associated with closing Fort Monmouth, N.J., and moving its functions to Aberdeen Proving Ground and Fort Meade, both in Maryland, and to Fort Belvoir.

The biggest increase came when the Army realized, after changes had begun, that it needed an additional 750,000 square feet of construction for the Command, Control, Communications, Computers, Intelligence, Surveillance and Reconnaissance Center of Excellence at Aberdeen.

Another element moved from Fort Monmouth was the Military Academy Preparatory School. Since before World War I, the school has been a vehicle for enlisted Army personnel to get a quick year's education, primarily in math and English, so they can qualify for admission to West Point. In 1965, it opened to civilians "who had proven themselves as leaders and athletes," giving them "another avenue to enter West Point," according to the school's Website.

At Fort Monmouth, the academy was housed in a 45-year-old Signal Corps School complex. Now, it's moving into a facility that an Army publication described in 2011 as "a typical large Military Construction project" with barracks and a gymnasium, along "with three NCAA sports fields (and) an academic building with a dining facility that serves 300."

According to the GAO, the project has "experienced about a $127 million or 449-percent increase over initial (BRAC) estimates."

In another instance, about $347 million was added to the cost of realigning supply and storage facilities around the country, in part because one request for 20,000 square feet of space turned out to be a typographical error: 200,000 square feet was actually needed, requiring additional construction, according to the GAO.

That was at Georgia's Warner Robins Strategic Distribution Platform.

Even small BRAC projects experienced giant cost growth.

"Local commanders saw an opportunity to upgrade their facilities," remarked a retired general.

At Fort Jackson in Columbia, for example, the price tag for two projects grew by more than 1,000 percent. One of them, the Single Drill Sergeant School, was supposed to cost $1.8 million. But when the Army determined that its 40-year-old facilities needed new classrooms, headquarters offices and a dining area for 250 additional students, the project's cost grew to $27.2 million, the GAO reports.

The military didn't initiate all the increases. For example, the GAO attributed much of the $1.7 billion rise in the cost of moving the Walter Reed Army Medical Center to the National Naval Medical Center to a congressionally mandated study that found that Walter Reed and a new military hospital at Fort Belvoir "should be 'world-class' medical facilities." Given the need for better care of the wounded and ill from Iraq and Afghanistan, no one could deny that spending.

Should all this mean no more BRAC? Of course not. Despite the billions in cost increases, the 2005 BRAC -- with roughly 180 closed or realigned bases or programs -- is resulting in an average savings of nearly $4 billion a year, according to the GAO.

Just keep closer tabs when the next round is approved.

The Island Packet is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.